Wednesday, 27 September 2017

After completion of the restoration of the tower the scaffolding came down, the new drainage system was started. Installed on the West side of the Church it is expected to make a dramatic improvement of the church fabric.


 

Internal restoration of the church is making good progress, with cracks above the East window repaired.



Like wise the internal cracks in the tower have been repaired, know the tower restoration has been completed


The foundations and tiling have been completed, ready for the font to be re-positioned

Thursday, 21 September 2017


The continued success of our HLF Schools Project is not only due to the continued support of our qualified helpers, but also the support of commercial organisations. Over five hundred school children have visited the Ovington project so far, and with the very generous support of Tesco supermarket every pupil has been provided with fresh fruit. On a weekly basis fruit and refreshments are collected from the local Watton supermarket and given the pupils in their break times




The fresh fruit manager Jacob and his colleagues have been extremely supportive and helpful in aiding the success of the project.


Jacob made us very much aware it is the company’s policy to support this type on community project, especially as it was including most of the local schools. He said this helps them to encourage healthy eating in children via our project, as well as when children visit their stores. Thank you Tesco












Tuesday, 12 September 2017

The Weather continues to be good, the church roof gets its repairs started.











The old lead removed and eventually replaced with better non-lead materials.